Tanker laytime and demurrage calculation

Updated 2026-10-06 · About 8 min read

In one sentence

Calculate allowed laytime under the charter, start at the earlier of notice expiry or all fast, deduct agreed exceptions, then prorate demurrage after expiry.

Calculation steps

  1. 1

    Set allowed laytime

    ASBATANKVOY uses the running hours agreed in Part I for loading and discharge combined. Other charters may use cargo quantity divided by handling rate; follow the contract.[S6]

  2. 2

    Set commencement

    Under ASBATANKVOY clause 6, time starts six hours after NOR is received or when the vessel is all fast, whichever comes first.[S6]

  3. 3

    List exceptions

    Deduct only periods specified by the charter, including anchorage-to-berth travel, ballast and slop discharge, vessel-caused delays, and night work prohibited by owners or port authorities. Charterer-prohibited night work counts.[S6]

  4. 4

    Handle shifting

    Under ASBATANKVOY clause 9, shifting between berths at the charterer's request counts as laytime, subject to clause 15 and the contract text.[S6]

  5. 5

    Find expiry

    Accumulate only counted time from commencement until allowed hours are used. Later hours are demurrage. A day is 24 consecutive hours, with fractions prorated.[S4]

  6. 6

    Calculate demurrage

    Multiply demurrage hours by the daily rate divided by 24. ASBATANKVOY specifies half rate for certain causes. Whether exceptions continue after expiry depends on the charter; BIMCO's 2013 definition disapplies them unless agreed otherwise.[S6][S4]

Worked example (synthetic data)

ExampleSynthetic data · Demo Tanker A
NOR tendered
1 Mar 06:00
Anchorage to berth
2 Mar 05:30
All fast
2 Mar 08:00
Shifting within port
3 Mar 20:00–22:00
Vessel pump failure
4 Mar 10:00–13:00
Weather stoppage
4 Mar 20:00–23:00
Hoses disconnected
5 Mar 04:00
Allowed laytime
72.0 hours
Excluded time
5.5 hours
Demurrage time
10.5 hours
Demurrage amount
USD 8,750.00

All dates, quantities, rates, and vessel details are synthetic and illustrate the method only.

Try a calculation

Enter NOR, working times, and exceptions to estimate demurrage or despatch.

Open laytime calculator →

Calculation

  • Allowed time: 18,000 ÷ 250 = 72.0 hours.
  • NOR at 06:00 plus six hours gives 1 March 12:00; all fast is later, so timing starts at 12:00.
  • Count 17.5 hours until 2 March 05:30.
  • Deduct 2.5 hours for travel from anchorage to berth.
  • Count 50.0 hours from 2 March 08:00 to 4 March 10:00, including two hours of shifting. Cumulative: 67.5 hours.
  • Deduct three hours of pump failure.
  • Count another 4.5 hours from 13:00; laytime expires at 4 March 17:30.
  • The next 10.5 hours are demurrage. The three-hour weather stoppage counts under this example's assumption.
  • Demurrage: 10.5 ÷ 24 × USD 20,000 = USD 8,750.00.
  • Reconciliation: 88.0 elapsed hours = 72.0 used + 5.5 excluded + 10.5 demurrage.
  • If weather remains excepted during demurrage, demurrage becomes 7.5 hours and USD 6,250.00. The calculator switch models this. The charter party terms and the governing law decide.

Common mistakes

  • Treating NOR tender as commencement. ASBATANKVOY has a six-hour notice period or earlier all-fast time; follow the actual charter.[S6]
  • Carrying laytime exceptions into demurrage automatically. BIMCO's 2013 definition stops them unless the charter says otherwise.[S4]
  • Failing to deduct vessel-caused delays such as pump failure, insufficient capacity, or ballast discharge.[S6]
  • Deducting all shifting. Charterer-requested berth-to-berth shifting counts under ASBATANKVOY; anchorage-to-berth travel does not.[S6]
  • Mixing days and hours. A day is 24 consecutive hours, and partial demurrage hours are prorated rather than rounded to half days.[S6][S4]
  • Mixing time zones. Put all records in one time zone before calculating and follow the charter and statements of facts.

Questions

Can NOR be tendered before the laycan starts?

Check the charter. In the cited ASBATANKVOY contract, NOR at the load port before the first layday needs charterer consent. Check Part I and riders.

What if operations start during the six-hour notice period?

ASBATANKVOY clause 6 starts at the earlier of six hours after NOR or all fast. A separate 'unless sooner commenced' clause applies only if incorporated.

How does reversible laytime differ from separate calculation?

Reversible laytime lets unused load-port time carry to discharge. Under an average arrangement, savings and overruns are computed separately and offset. Follow the charter.

Is demurrage always charged at full rate?

No. ASBATANKVOY clause 8 applies half rate to specified fire, explosion, storm, strike, and machinery delays. Check any other charter adjustments.

When does timing stop?

This page defaults to hoses disconnected. Adjust the endpoint if the charter provides otherwise.